Fact sheet
November 2026 · shamsalshamsolarpark.com
November 2026 · shamsalshamsolarpark.com
Wedian Al-Rabie Solar Park, Syria
Three solar power plants and two battery stations on one site near Damascus, owned by the Shams Al-Sham project companies and sponsored by Mohammed Ahmad Al-Harfi Contracting Co. (MAH).
- 760MWpsolar capacity, more than a million panels
- 1,077MWhbattery storage for evening supply
- 1.7bn kWh/yrclean electricity to the national grid
- 2,000+Syrian workers trained and employed
The three plants
| Plant | Solar | Battery | Role |
|---|---|---|---|
| Plant 1 | 287.7 MWp | 827 MWh | Largest plant and battery; about four hours of full output into the evening |
| Plant 2 | 198.7 MWp | 250 MWh | Battery smooths output and supports the grid around sunrise and sunset |
| Plant 3 | 274 MWp | — | Solar only, direct to the grid through the day |
| All three connect through one shared 400 kV substation on site, built once and used by all. Each plant has its own project company and its own long-term power purchase agreement. | |||
Who is building it
- Sponsor: Mohammed Ahmad Al-Harfi Contracting Co. (MAH), Riyadh
- Construction: Kawar Energy – ZTT Joint Venture (Jordan / China), EPC contractor; operator Kawar Energy
- Owner's engineer: Arbutus Consultants
- Electricity buyer: Ministry of Energy and the Public Establishment for Electricity
- Jobs programme: with the International Labour Organization (ILO)
- Advisors: Eversheds Sutherland (legal), Gridlines (financial), Saudi Electricity Project Development Co. — PDC (technical and commercial)
Community and environment
- At least 2,000 Syrian workers recruited and trained before and during construction
- Vocational training centre that stays open after the build
- Site canteen (around 2,000 meals a day) run by women from nearby communities
- Environmental and social assessment to IFC Performance Standards
Timeline
| 16 February 2026 | Binding memorandum of understanding signed with the Syrian Ministry of Energy in Damascus |
| Spring 2026 | Development, site studies, environmental and social assessment |
| July 2026 | Power purchase agreements concluded for all three plants |
| 5 August 2026 | Signing ceremony in Damascus, under the supervision of the Saudi Ministry of Energy |
| November 2026 | Groundbreaking at Wedian Al-Rabie |
| 2027 onwards | Construction of the plants, battery stations and 400 kV substation |
| On completion | First power to the grid |
Where
Wedian Al-Rabie, Rural Damascus Governorate, Syrian Arab Republic — open land close to Damascus International Airport and to the high-voltage lines serving Damascus.
Contact
info@shamsalshamsolarpark.com
shamsalshamsolarpark.com
© 2026 Shams Al-Sham — Saudi-Syrian Company for Power Generation
Figures are design values and may be refined during construction.