Wedian Al-Rabie Solar Park, Syria

Three solar power plants and two battery stations on one site near Damascus, owned by the Shams Al-Sham project companies and sponsored by Mohammed Ahmad Al-Harfi Contracting Co. (MAH).

The three plants

PlantSolarBatteryRole
Plant 1287.7 MWp827 MWhLargest plant and battery; about four hours of full output into the evening
Plant 2198.7 MWp250 MWhBattery smooths output and supports the grid around sunrise and sunset
Plant 3274 MWp—Solar only, direct to the grid through the day
All three connect through one shared 400 kV substation on site, built once and used by all. Each plant has its own project company and its own long-term power purchase agreement.

Who is building it

  • Sponsor: Mohammed Ahmad Al-Harfi Contracting Co. (MAH), Riyadh
  • Construction: Kawar Energy – ZTT Joint Venture (Jordan / China), EPC contractor; operator Kawar Energy
  • Owner's engineer: Arbutus Consultants
  • Electricity buyer: Ministry of Energy and the Public Establishment for Electricity
  • Jobs programme: with the International Labour Organization (ILO)
  • Advisors: Eversheds Sutherland (legal), Gridlines (financial), Saudi Electricity Project Development Co. — PDC (technical and commercial)

Community and environment

  • At least 2,000 Syrian workers recruited and trained before and during construction
  • Vocational training centre that stays open after the build
  • Site canteen (around 2,000 meals a day) run by women from nearby communities
  • Environmental and social assessment to IFC Performance Standards

Timeline

16 February 2026Binding memorandum of understanding signed with the Syrian Ministry of Energy in Damascus
Spring 2026Development, site studies, environmental and social assessment
July 2026Power purchase agreements concluded for all three plants
5 August 2026Signing ceremony in Damascus, under the supervision of the Saudi Ministry of Energy
November 2026Groundbreaking at Wedian Al-Rabie
2027 onwardsConstruction of the plants, battery stations and 400 kV substation
On completionFirst power to the grid

Where

Wedian Al-Rabie, Rural Damascus Governorate, Syrian Arab Republic — open land close to Damascus International Airport and to the high-voltage lines serving Damascus.